Highway 15 work wrapping up

Ribbon cutting is 2 p.m. Dec. 12 on the square

Posted

If you have not yet noticed, Highway 15 through Seward is open.

With a few small spots where concrete was still curing or rights of way and sidewalks were to be cleaned, workers had finished work on the 1.1-mile, $9.9 million reconstruction project as December began, meeting the city’s target date.

A celebratory ribbon cutting will begin at 2 p.m. Thursday, Dec. 12, on the Seward County Courthouse Square, according to City Administrator Greg Butcher.  

Butcher said “big kudos” are needed for the Nebraska Department of Transportation team, led by Highway Project Manager Brian Schoen, the Constructors team and city staff who have worked on the project.

The work was originally expected to take two years. It has taken just one year, but not without some challenges and stress.

“We are kind of suffering from one-year-of-construction fatigue,” Butcher said. “It’s nice to have a little relief.”

Butcher said residents have commented about the sheer number of capital improvement projects going on in Seward this year.

“This is the most they have ever seen going on at one time in Seward. And we are like, yeah. It’s a lot.” Butcher said.

Some grass planting, curb cleanup and other finishing touches will be tackled in March or April, Butcher said.

The Highway 15 reconstruction project began just south of the Burlington Northern Santa Fe Railroad crossing and continues to North Avenue, adding a two-way left turn center lane from Jackson Avenue to North Avenue, a new right turn lane near the high school, and resurfacing from North Avenue to Pinewood Avenue. 

In conjunction with the project, the city has also had crews replacing storm sewers and making other updates to the areas being reconstructed. Some unanticipated projects necessitated by aging water mains, utility lines, ground conditions, and weather issues also had to be addressed.

In the spring, the city hopes to complete the work around the new water tower, complete its decorative painting and begin removing the old water tower, but none of those projects should interfere with Highway 15 traffic.

The area under the tower has been made a parking lot and will eventually have a few “telecommunication huts” for area service providers. When the old tower is removed, that area will be utilized by the city streets department to facilitate the movement of heavy equipment.

The painting project, which was to have begun this fall, awaits warmer temperatures after the original contractor incurred some problems. 

Other spring projects will include work on Worthman Road, the main road into the Rail Campus south of downtown and west of Highway 15, and roadwork on Hillcrest Drive east to the Plum Creek bridge, which will include the addition of a paved trail connecting the existing biking and walking trails from one side of Hilcrest to the other. 

Seward’s new wastewater treatment plant project – which Butcher said will likely be the largest capital expenditure the city will ever have taken on – remains in the design stage as city officials continue to work on funding options for the $32 million facility.

Butcher said the city has exercised due diligence by implementing rate increases to save some funds for the project. They continue to seek state and/or federal grant and loan programs for assistance.